51 practice questions on Time & Work from the Quantitative Aptitude section of the UPSC Prelims syllabus.
51 come with a written explanation and 13 are actual previous year questions.
Try the sample set below - the answer stays hidden until you ask for it.
11 Easy31 Medium9 Hard13 from past papers
Sample questions
Q1
Previous year questionhard
A set (X) of 20 pipes can fill 70% of a tank in 14 minutes. Another set (Y) of 10 pipes fills 3/8th of the tank in 6 minutes. A third set (Z) of 16 pipes can empty half of the tank in 20 minutes. If half of the pipes of set X are closed and only half of the pipes of set Y are open, and all pipes of the set (Z) are open, then how long will it take to fill 50% of the tank?
A8 minutes
B10 minutes
C12 minutes
D16 minutes
Show answer and explanation
Correct answer: D - 16 minutes
Find rates as fraction of tank per minute. Set X: 20 pipes fill 0.70 in 14 min -> 0.05/min, so one X pipe = 0.0025. Set Y: 10 pipes fill 0.375 in 6 min -> 0.0625/min, one Y pipe = 0.00625. Set Z: 16 pipes empty 0.5 in 20 min -> 0.025/min, one Z pipe = 0.0015625. Now half of X closed = 10 X pipes open: 10 x 0.0025 = 0.025. Half of Y open = 5 Y pipes: 5 x 0.00625 = 0.03125. All Z open (emptying): -0.025. Net = 0.025 + 0.03125 - 0.025 = 0.03125 tank/min. Time to fill 50% (0.5) = 0.5 / 0.03125 = 16 minutes. Answer: (d).
Q2
Previous year questionmedium
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
A3 : 1 : 1
B3 : 2 : 4
C4 : 3 : 4
D3 : 1 : 4
Show answer and explanation
Correct answer: A - 3 : 1 : 1
Earnings are shared in proportion to work done, i.e. to the rates of work. Let Q's rate = 1 unit. P works thrice as fast as Q, so P's rate = 3. P and Q together work four times as fast as R: (P + Q) = 4R, so R = (3 + 1)/4 = 1. Thus the rates are P : Q : R = 3 : 1 : 1, which is also the ratio of work done (and hence earnings). Hence (a).
Q3
Previous year questionmedium
X can complete one-third of a certain work in 6 days, Y can complete one-third of the same work in 8 days and Z can complete three-fourth of the same work in 12 days. All of them work together for n days and then X and Z quit and Y alone finishes the remaining work in 8 2/3 days. What is n equal to?
A3
B4
C5
D6
Show answer and explanation
Correct answer: B - 4
X does one third of the work in 6 days, so X alone takes 18 days and works at 1/18 per day. Y does one third in 8 days, so Y takes 24 days and works at 1/24 per day. Z does three fourths in 12 days, so Z takes 16 days and works at 1/16 per day. Combined rate = 1/18 + 1/24 + 1/16 = (8 + 6 + 9)/144 = 23/144 per day. Y alone finishes the remainder in 8 2/3 = 26/3 days, completing (26/3) x (1/24) = 26/72 = 13/36 of the work. So the three together did 1 - 13/36 = 23/36 = 92/144 of the work in n days: (23/144) x n = 92/144, giving n = 4. The official UPSC key confirms option (b).
Q4
Previous year questionmedium
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A30 days
BMore than 30 days
CLess than 30 days or more than 30 days
DData is inadequate to draw any conclusion
Show answer and explanation
Correct answer: D - Data is inadequate to draw any conclusion
Let a man do m units per day and a woman w units per day. The given data yields one equation, 30(24m + 12w) = total work, with two unknown efficiencies. The required time for 12 men and 24 women depends on the sign of (12m + 24w) - (24m + 12w) = 12(w - m), which is unknown: if w = m the answer is exactly 30 days, if w > m it is less, and if w < m it is more. Option (a) assumes equal efficiency, option (b) assumes men are more efficient, and option (c) wrongly excludes the possibility of exactly 30 days. Since no relation between m and w is given, only option (d), data inadequate, is correct.
Q5
Previous year questionmedium
A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
A6
B8
C10
D12
Show answer and explanation
Correct answer: A - 6
X completes 20% in 8 days, so X completes the full work in 8 x 5 = 40 days, rate = 1/40 per day. Y completes 25% in 6 days, so Y completes the full work in 6 x 4 = 24 days, rate = 1/24 per day. Combined rate = 1/40 + 1/24 = (3 + 5)/120 = 8/120 = 1/15 of the work per day. Time to complete 40% (= 0.4 work) = 0.4 / (1/15) = 0.4 x 15 = 6 days. The other options come from miscomputing individual full-work times or the combined rate.
Q6
Previous year questionmedium
W can do 25% of a work in 30 days, X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first?
AW
BX
CY
DZ
Show answer and explanation
Correct answer: D - Z
Scale each rate to the whole job. W does 25% in 30 days, so the full job takes 30 x 4 = 120 days. X does 1/4 in 10 days, so the full job takes 10 x 4 = 40 days. Y does 40% in 40 days, so the full job takes 40 x (100/40) = 100 days. Z does 1/3 in 13 days, so the full job takes 13 x 3 = 39 days. The smallest time is Z's 39 days, so Z finishes first (just ahead of X's 40 days). Hence Z.
Q7
Previous year questionmedium
A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements:
1. The work will be finished on Thursday.
2. The work will be finished in 10 days.
Which of the above statements is/are correct?
A1 only
B2 only
CBoth 1 and 2
DNeither 1 nor 2
Show answer and explanation
Correct answer: A - 1 only
Option (a) is correct. Daily work in 48ths of the job: A does 6, B does 3, C does 4. The rotation A, B, C starts on Monday and repeats every three days. Cumulative work: after day 3 (Wed) 13/48, day 6 (Sat) 26/48, day 9 (Tue) 39/48, day 10 (Wed, A) 45/48. On day 11 B contributes exactly the remaining 3/48, finishing the job at the end of day 11. Counting weekdays from Monday as day 1, day 11 is a Thursday, so statement 1 is correct. Statement 2 is wrong because the work takes 11 days, not 10; after 10 days only 45/48 is done. Hence options (b), (c) and (d) fail.
Q8
Previous year questioneasy
A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?
A10%
B(50/3)%
C20%
D25%
Show answer and explanation
Correct answer: C - 20%
Total work = M x 6k man-days for M men. To finish the same work in 5k days, the required number of men is M' = (M x 6k) / 5k = 1.2M. The increase is 0.2M, i.e., 20% of the original number of men. Hence 20%.
Practice all 51 Time & Work questions free
Timed practice, instant scoring, and explanations for every question. Free forever - no card, no catch.